Gallery / Monthly Progress Photos. / April 2011

CLIENT/PMC SITE OFFICE CONSTRUCTION COMPLETED

BATCHING PLANT ERECTION WORKS IN PROGRESS

FOOTING RCC WORKS IN PROGRESS IN BLOCK-B

RETAINING WALL CONCRETING IN PROGRESS IN BLOCK B

COLUMN CONCRETING & BACK FILLING WORKS IN POGRESS FOR BLOCK B

SHUTTERING WORKS FOR CELLAR SLAB IN PROGRESS FOR BLOCK B

ROCK ANCHORAGE & PCC WORK IN PROGRESS -BLOCK ‘C’

FOUNDATION RCC  WORK IN PROGRESS- BLOCK ‘C’

ROCK ANCHORAGE & PCC WORK IN PROGRESS FOR BLOCK-‘A’

SHUTTERING & REINFORCEMENT WORK IN PROGRESS FOR FOUNDATION OF BLOCK ‘A’

FOUNDATION EXCAVATION IN PROGRESS IN BLOCK ‘D’

R. WALL FOUNDATION EXCAVATION IN PROGRESS IN BLOCK ‘D’