BLOCK B- FIRST FLOOR SLAB CONCRETING COMPLETED ON 1stOCTOBER 2011
BLOCK B: FIRST FLOOR SLAB CONCRETING COMPLETD ON 1st OCTOBER 2011 – NORTH VIEW
BLOCK B – BLOCK WORK AT GROUND FLOOR COMMENCED ON 24th SEP 2011
BLOCK B: PLINTH BEAM CONCRETING IN PROGRESS
BLOCK B: BLOCK WORK AT GROUND FLOOR COMMENCED ON 24th SEP 2011
BLOCK B: BLOCK WORK AT GROUND FLOOR IN PROGRESS
BLOCK C: CELLAR SLAB CONCRETING COMPLETED ON 22nd SEP 2011
BLOCK C: COLUMN CONCRETING ABOVE CELLAR SLAB COMPLETED ON 22nd SEP 2011
BLOCK A : SUB-CELLAR SLAB CONCRETING COMPLETED ON 18th SEP 2011 EXCEPT SLAB AT FIRE SUMP
BLOCK A : CELLAR SLAB SHUTTERING & REINFORCEMENT WORKS IN PROGRESS
BLOCK D : SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
BLOCK B: CELLAR CEILING PLASTER WORK IN PROGRESS
FIRE ESCAPE STAIR CONCRETING WORK IN PROGRESS
BACK FILLING WORK IN PROGRESS AT EXTERNAL SIDE OF RT. WALL
FLY ASH BLOCK MAKING AT SITE IN PROGRESS