Gallery / Monthly Progress Photos. / August 2011

BLOCK B- CELLAR SLAB CONCRETING COMPLETED ON 31st JULY 2011

BLOCK B – COLUMN CONCRETING ABOVE CELLAR LVL IN PROGRESS AS ON 13th AUG 2011

BLOCK B: GROUND FLOOR SLAB CONCRETING COMPLETD ON 30th AUGUST 2011 –     EAST VIEW

BLOCK  B: GROUND FLOOR SLAB CONCRETING COMPLETD ON 30th AUGUST 2011 – NORTH EAST TOP VIEW

BLOCK C: SUB-CELLAR CONCRETING WORK IN PROGRESS

BLOCK C: COLUMNS & RETAINING WALL CONCRETING ABOVE SUB-CELLAR SLAB LEVEL IN PROGRESS

BLOCK C: CELLAR SLAB BEAM SHUTTERING & REINFORCEMENT WORKS IN PROGRESS – TOP VIEW

BLOCK A: COLUMNS & RETAINING WALL CONCRETING IN PROGRESS

BLOCK A : SUB-CELLAR SLAB SHUTTERING WORKS IN PROGRESS

BLOCK A : SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT  WORKS IN PROGRESS

BLOCK D : FOOTING & COLUMN RCC WORKS IN PROGRESS

BLOCK D : SUB-CELLAR SLAB SHUTTERING WORK  IN PROGRESS

BLOCK D : SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORK  IN PROGRESS

RETAINING WALL : WATER PROOFING PLASTER WORKS IN PROGRESS