Gallery / Monthly Progress Photos. / May 2011

BATCHING PLANT  & SILOS ERECTION COMPLETED

BATCHING PLANT  BINS LOADED WITH AGGREGATES

CONSTRUCTION OF QC LAB COMPLETED

250 KVA TRANFORMER  INSTALLED AT SITE AND CABLE LAYING WORKS IN PROGRESS

CELLAR SLAB SHUTTERING WORK IN PROGRESS  BLOCK B

SHUTTERING & REINFORCEMENT WORK IN PROGRESS FOR CELLAR SLAB OF BLOCK B

FOOTING & COLUMN WORKS IN POGRESS FOR BLOCK C

RETAINING WALL CONCRETING IN PROGRESS IN BLOCK C

ROCK ANCHORAGE & PCC WORK IN PROGRESS -BLOCK A

RETAINING WALL PCC  WORK IN PROGRESS- BLOCK A

FOOTING RCC WORKS IN PROGRESS IN BLOCK-A

EXCAVATION WORK IN PROGRESS IN BLOCK -D