Gallery / Monthly Progress Photos. / October 2011

SUBSURFACE DRAINAGE PIPELINE LAYING WORKS  IN PROGRESS

SUBSURFACE DRAINAGE PIPELINE LAYING & BACK FILLING WORKS  IN PROGRESS

BLOCK-B: COLUMN CONCRETING &SLAB SHUTTERING WORK IN PROGRESS FOR 2nd FLOOR SLAB

BLOCK-B: 2nd FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

BLOCK-C: GROUND FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

BLOCK-A: CELLAR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

BLOCK-D: SUB-CELLAR SLAB CONCRETING COMPLETED ON 23RD OCT 2011

BLOCK-D: COLUMN CONCRETING & SHUTTERING WORK IN PROGRESS FOR CELLAR SLAB

IN B/W BLOCKS B & C: CASTING OF FOOTINGS & COLUMNS IN PROGRESS.

IN B/W BLOCKS B & C: CASTING OF FOOTINGS & COLUMNS IN PROGRESS.

BLOCK-B; BLOCK WORK IN PROGRESS AT GROUND FLOOR & FIRST FLOOR.

BLOCK-B; BLOCK WORK IN PROGRESS AT GROUND FLOOR & FIRST FLOOR.

BLOCK-C: CEILING PLASTERING WORKS IN PROGRESS AT CELLAR AND SUB CELLAR AREAS.

BLOCK-A: CEILING PLASTERING WORKS IN PROGRESS AT SUBCELLAR AREA.

BLOCK –B: WALL CHASING WORKS IN PROGRESS FOR CONDUITING WORKS AT GROUND FLOOR.

BLOCK –B: WALL CHASING WORKS IN PROGRESS FOR CONDUITING WORKS AT GROUND FLOOR.