Gallery / Monthly Progress Photos. / January 2012

BLOCK-B: 5th FLOOR SLAB CONCRETING COMPLETED ON 22nd JAN 2012

BLOCK-B: COLUMN CONCRETING IN PROGRESS FOR 6th FLOOR SLAB

BLOCK-C: 3rd FLOOR SLAB CONCRETING COMPLETED ON 17th JAN 2012

BLOCK-C: 4th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

BLOCK-A: 1st FLOOR SLAB CONCRETING COMPLETED ON 14th JAN 2012

BLOCK-A: 2nd FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

BLOCK-D: GROUND FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

IN B/W BLOCKS B & C: COLUMN CONCRETING FOR CELLAR SLAB IN PROGRESS

IN B/W BLOCK A&B: COLUMN CONCRETING IN PROGRESS FOR RAMP AT SUB-CELLAR LEVEL

IN B/W BLOCK C&D: FOUNDATION & COLUMN CONCRETING IN PROGRESS FOR RAMP AT SUB-CELLAR LEVEL

STORM WATER SUMP CONCRETING IN PROGRESS

BLOCK-B: SUNKEN WATER PROOFING WORKS IN PROGRESS

BLOCK-A: BLOCK WORK AT GROUND FLOOR IN PROGRESS

BLOCK WORK IN PROGRESS AT BLOCK B & BLOCK C

LINTELS CONCRETING IN PROGRESS

BLOCK B: 1ST COAT PLASTERING, ELECTRICAL CONDUTING & AC DRAIN POINT WORK IN PROGRESS AT 1ST FLOOR