BLOCK-B: 5th FLOOR SLAB CONCRETING COMPLETED ON 22nd JAN 2012
BLOCK-B: COLUMN CONCRETING IN PROGRESS FOR 6th FLOOR SLAB
BLOCK-C: 3rd FLOOR SLAB CONCRETING COMPLETED ON 17th JAN 2012
BLOCK-C: 4th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
BLOCK-A: 1st FLOOR SLAB CONCRETING COMPLETED ON 14th JAN 2012
BLOCK-A: 2nd FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
BLOCK-D: GROUND FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
IN B/W BLOCKS B & C: COLUMN CONCRETING FOR CELLAR SLAB IN PROGRESS
IN B/W BLOCK A&B: COLUMN CONCRETING IN PROGRESS FOR RAMP AT SUB-CELLAR LEVEL
IN B/W BLOCK C&D: FOUNDATION & COLUMN CONCRETING IN PROGRESS FOR RAMP AT SUB-CELLAR LEVEL
STORM WATER SUMP CONCRETING IN PROGRESS
BLOCK-B: SUNKEN WATER PROOFING WORKS IN PROGRESS
BLOCK-A: BLOCK WORK AT GROUND FLOOR IN PROGRESS
BLOCK WORK IN PROGRESS AT BLOCK B & BLOCK C
LINTELS CONCRETING IN PROGRESS
BLOCK B: 1ST COAT PLASTERING, ELECTRICAL CONDUTING & AC DRAIN POINT WORK IN PROGRESS AT 1ST FLOOR