BLOCK-B: 7th FLOOR SLAB CONCRETING COMPLETED ON 6th MARCH 2012
BLOCK-B: 8th FLOOR SLAB CONCRETING COMPLETED ON 28th MARCH 2012
BLOCK-C: 6th FLOOR SLAB CONCRETING COMPLETED ON 15th MARCH 2012
BLOCK-C: 7th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
BLOCK-A: 4th FLOOR SLAB CONCRETING COMPLETED ON 20th MARCH 2012
BLOCK-A: 5th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
BLOCK-D: 2nd FLOOR SLAB CONCRETING COMPLETED ON 22nd MARCH 2012
BLOCK-D: 3rd FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
IN B/W BLOCK A&B: CONCRETING FOR RAMP AT SUB-CELLAR SLAB COMPLETED ON 7th MARCH 2012
IN B/W BLOCK A&B: CONCRETING FOR SUB-CELLAR SLAB COMPLETED ON 20th MARCH 2012
IN B/W BLOCK C&D: CONCRETING FOR RAMP AT SUB-CELLAR SLAB COMPLETED ON 2nd MARCH 2012
BLOCK-B: BLOCK WORK COMPLETED AT GROUND & 1st FLOOR , WORK IN PROGRESS AT 2nd, 3rd, 4th & 5th FLOOR
BLOCK-C: BLOCK WORK COMPLETED AT GROUND & WORK IN PROGRESS AT 1st & 2nd FLOOR
BLOCK-A:BLOCK WORK IN PROGRESS AT GROUND &1st FLOOR
BLOCK-D: BLOCK WORK COMMENCED AT GROUND FLOOR ON 26th MARCH 2012
FLOORING WORK IN PROGRESS AT MOCKUP FLAT (102) OF BLOCK B
PLUMBING WORK IN PROGRESS AT MASTER BEDROOM TOILET(102) OF BLOCK B
INTERNAL SUB-SURFACE DRAINAGE WORK IN PROGRESS AT BLOCK A & BLOCK D