Gallery / Monthly Progress Photos. / April 2012

BLOCK-B: 9th FLOOR SLAB CONCRETING COMPLETED ON 19th APRIL 2012

BLOCK-B: COLUMN CONCRETING FOR 10th FLOOR SLAB IN PROGRESS

BLOCK-C: 8th FLOOR SLAB CONCRETING COMPLETED ON 26th APRIL 2012

BLOCK-C: COLUMN CONCRETING IN PROGRESS FOR 9th FLOOR SLAB

BLOCK-A: 5th FLOOR SLAB CONCRETING COMPLETED ON 11th APRIL 2012

BLOCK-A: 6th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

BLOCK-D: 3rd FLOOR SLAB CONCRETING COMPLETED ON 12th APRIL 2012

BLOCK-D: 4th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

IN B/W BLOCK A&B: CONCRETING FOR CELLAR SLAB COMPLETED ON 30th APRIL 2012

IN B/W BLOCK C&D: SHUTTERING FOR SUB-CELLAR SLAB IN PROGRESS

BLOCK-B: BLOCK WORK  COMPLETED UP TO 3rd FLOOR , WORK IN PROGRESS AT 4th, 5th & 6th FLOOR

BLOCK-C: BLOCK WORK  COMPLETED AT GROUND  & 1st FLOOR, WORK IN PROGRESS AT 2nd & 3rd FLOOR

BLOCK-A: BLOCK WORK  COMPLETED AT GROUND  FLOOR, WORK IN PROGRESS AT 1st & 2nd FLOOR

BLOCK-D: BLOCK WORK IN PROGRESS AT GROUND & 1st FLOOR

EXTERNAL  CHAMBERS CONCRETING WORK IN PROGRESS AT EAST SIDE OF RT. WALL

MOCK UP FLAT-BLOCK B(102): INTERNAL DOOR INSTALLATION COMPLETED

MOCK UP FLAT-BLOCK B(102): KITCHEN PLATFORM WORKS INCLUDING SINK INSTALLATION COMPLETED

MOCK UP FLAT-BLOCK B(102): TOILET WASH BASIN & CP FITTINGS INSTALLATION COMPLETED