BLOCK-B: 9th FLOOR SLAB CONCRETING COMPLETED ON 19th APRIL 2012
BLOCK-B: COLUMN CONCRETING FOR 10th FLOOR SLAB IN PROGRESS
BLOCK-C: 8th FLOOR SLAB CONCRETING COMPLETED ON 26th APRIL 2012
BLOCK-C: COLUMN CONCRETING IN PROGRESS FOR 9th FLOOR SLAB
BLOCK-A: 5th FLOOR SLAB CONCRETING COMPLETED ON 11th APRIL 2012
BLOCK-A: 6th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
BLOCK-D: 3rd FLOOR SLAB CONCRETING COMPLETED ON 12th APRIL 2012
BLOCK-D: 4th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
IN B/W BLOCK A&B: CONCRETING FOR CELLAR SLAB COMPLETED ON 30th APRIL 2012
IN B/W BLOCK C&D: SHUTTERING FOR SUB-CELLAR SLAB IN PROGRESS
BLOCK-B: BLOCK WORK COMPLETED UP TO 3rd FLOOR , WORK IN PROGRESS AT 4th, 5th & 6th FLOOR
BLOCK-C: BLOCK WORK COMPLETED AT GROUND & 1st FLOOR, WORK IN PROGRESS AT 2nd & 3rd FLOOR
BLOCK-A: BLOCK WORK COMPLETED AT GROUND FLOOR, WORK IN PROGRESS AT 1st & 2nd FLOOR
BLOCK-D: BLOCK WORK IN PROGRESS AT GROUND & 1st FLOOR
EXTERNAL CHAMBERS CONCRETING WORK IN PROGRESS AT EAST SIDE OF RT. WALL
MOCK UP FLAT-BLOCK B(102): INTERNAL DOOR INSTALLATION COMPLETED
MOCK UP FLAT-BLOCK B(102): KITCHEN PLATFORM WORKS INCLUDING SINK INSTALLATION COMPLETED
MOCK UP FLAT-BLOCK B(102): TOILET WASH BASIN & CP FITTINGS INSTALLATION COMPLETED