BLOCK-B: 11th FLOOR SLAB CONCRETING COMPLETED ON 31st May 2012
BLOCK-B: 12TH FLOOR SLAB REINFORCEMENT WORKS IN PROGRESS
BLOCK-C: 9th FLOOR SLAB CONCRETING COMPLETED ON 24th May 2012
BLOCK-C: COLUMN REINFORCEMENT WORKS IN PROGRESS FOR 10th FLOOR SLAB
BLOCK-A: 7th FLOOR SLAB CONCRETING COMPLETED ON 27th May 2012
BLOCK-A: 8th FLOOR SLAB REINFORCEMENT WORK IN PROGRESS
BLOCK-D: 5th FLOOR SLAB CONCRETING COMPLETED ON 29TH May 2012
BLOCK-D: 6th FLOOR COLUMN REINFORCEMENT WORKS IN PROGRESS
IN B/W BLOCK C&D: COLUMN CONCRETING FOR CELLAR SLAB IN PROGRESS
IN B/W BLOCK C&D: SHUTTERING FOR RAMP AT CELLAR IN PROGRESS
BLOCK-B: BLOCK WORK COMPLETED UP TO 5TH FLOOR AND WORK IN PROGRESS AT 6TH, 7TH & 8TH FLOOR, EXTERNAL STAGING WORK IN PROGRESS
BLOCK-C: BLOCK WORK COMPLETED UP TO 3RD FLOOR AND WORK IN PROGRESS AT 4TH, 5TH & 6TH FLOORS
BLOCK-A: BLOCK WORK COMPLETED UPTO 2ND FLOOR AND IN PROGRESS AT 3RD & 4TH FLOOR
BLOCK-D: BLOCK WORK COMPLETED UPTO 1ST FLOOR AND IN PROGRES AT 2ND FLOOR.
STP: FOUNDATION CONCRETING COMPLETED & REINFORCEMENT WORK IN PROGRESS FOR WALL
STROM WATER DRAIN BASE WORK IN PROGRESS