Gallery / Monthly Progress Photos. / June 2012

BLOCK-B: 11th FLOOR SLAB CONCRETING COMPLETED ON 31st May 2012

BLOCK-A: 8th FLOOR SLAB CONCRETING COMPLETED ON 18th June 2012

BLOCK-C : 10th FLOOR SLAB CONCRETING COMPLETED ON 15th June 2012

BLOCK-D: 7th FLOOR SLAB CONCRETING COMPLETED ON 20th June 2012

BLOCK-B: BLOCK WORK  COMPLETED UP TO 7TH FLOOR AND WORK IN PROGRESS  AT 8TH & 9TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-C: BLOCK WORK  COMPLETED UP TO 5TH FLOOR AND WORK IN PROGRESS AT 6TH & 7TH  FLOORS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 4TH  FLOOR AND WORK IN PROGRESS AT 5TH FLOOR

BLOCK-D: BLOCK WORK COMPLETED UPTO 1ST FLOOR AND IN PROGRES AT 2ND  & 3RD FLOOR.

EXTERNAL PLASTER IN PROGRESS AT BLOCK B GROUND TO 5TH FLOOR- SOUTH SIDE

STP WORKS: WALL CONCRETING COMPLETED  AT BLOCK C

STROM WATER DRAIN WORK: RCC HUME PIPE LAYING WORK IN PROGRESS

IN B/W BLOCK C&D: CONCRETING OF RAMP AT CELLAR LEVEL COMPLETED