BLOCK-B: 13th FLOOR SLAB CONCRETING COMPLETED ON 13th July 2012
BLOCK-C : 12th FLOOR SLAB CONCRETING COMPLETED ON 26th July 2012
BLOCK-A: 10th FLOOR SLAB CONCRETING COMPLETED ON 28th July 2012
BLOCK-D: 9th FLOOR SLAB CONCRETING COMPLETED ON 31st July 2012
BLOCK-B: BLOCK WORK COMPLETED UP TO 9TH FLOOR AND WORK IN PROGRESS AT 10TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-C: BLOCK WORK COMPLETED UP TO 7TH FLOOR AND WORK IN PROGRESS AT 8TH & 9TH FLOORS, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-A: BLOCK WORK COMPLETED UPTO 5TH FLOOR AND WORK IN PROGRESS AT 6TH FLOOR
BLOCK-D: BLOCK WORK COMPLETED UPTO 2ND FLOOR AND IN PROGRES AT 3RD & 4TH FLOOR.
STP: RT.WALL CONCRETING COMPLETED & SUB-CELLAR SLAB SHUTTERING IN PROGRESS
POP WORKS IN PROGRESS AT FIRST FLOOR OF BLOCK B
PLUMBING WATER SUPPLY & LAYING WORK IN PROGRESS AT TOILETS IN ALL FOUR BLOCKS
PLUMBING WASTE & SOIL LAYING WORK IN PROGRESS AT TOILETS IN ALL FOUR BLOCKS