Gallery / Monthly Progress Photos. / July 2012

BLOCK-B: 13th FLOOR SLAB CONCRETING COMPLETED ON 13th July 2012

BLOCK-C : 12th FLOOR SLAB CONCRETING COMPLETED ON 26th July 2012

BLOCK-A: 10th FLOOR SLAB CONCRETING COMPLETED ON 28th July 2012

BLOCK-D: 9th FLOOR SLAB CONCRETING COMPLETED ON 31st July 2012

BLOCK-B: BLOCK WORK  COMPLETED UP TO 9TH FLOOR AND WORK IN PROGRESS  AT 10TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-C: BLOCK WORK  COMPLETED UP TO 7TH FLOOR AND WORK IN PROGRESS AT 8TH & 9TH  FLOORS, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 5TH  FLOOR AND WORK IN PROGRESS AT 6TH FLOOR

BLOCK-D: BLOCK WORK COMPLETED UPTO 2ND FLOOR AND IN PROGRES AT 3RD & 4TH FLOOR.

STP: RT.WALL CONCRETING COMPLETED & SUB-CELLAR SLAB SHUTTERING IN PROGRESS

POP WORKS IN PROGRESS AT FIRST FLOOR OF BLOCK B

PLUMBING WATER SUPPLY & LAYING WORK IN  PROGRESS AT TOILETS IN ALL FOUR BLOCKS

PLUMBING WASTE & SOIL LAYING WORK IN  PROGRESS AT TOILETS IN ALL FOUR BLOCKS