Gallery / Monthly Progress Photos. / October 2012

BLOCK-B: 18th FLOOR SLAB CONCRETING COMPLETED ON 20th Oct 2012

BLOCK-C : 17th FLOOR SLAB CONCRETING COMPLETED ON 30th Oct 2012

BLOCK-A: 15th FLOOR SLAB CONCRETING COMPLETED ON 26th Oct 2012

BLOCK-D: 12th FLOOR SLAB CONCRETING COMPLETED ON 17th Oct 2012

BLOCK-B: BLOCK WORK  COMPLETED UP TO 15TH FLOOR AND WORK IN PROGRESS  AT 16TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-C: BLOCK WORK  COMPLETED UP TO 12TH FLOOR AND WORK IN PROGRESS AT 13TH  FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 9TH  FLOOR AND WORK IN PROGRESS AT 10TH FLOOR , EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-D: BLOCK WORK COMPLETED UPTO 8TH FLOOR AND IN PROGRES AT 9TH FLOOR.

SWIMMING POOL AREA: SUMP RAFT & WALL CONCRETING IN PROGRESS

CLUB HOUSE AREA: FOOTING & COLUMN CONCRETING IN PROGRESS

MEP (SERVICES) WORKS IN PROGRESS AT CELLAR AREA OF ALL THE FOUR BLOCKS

MEP (SERVICES) WORKS IN PROGRESS AT CELLAR AREA OF ALL THE FOUR BLOCKS