BLOCK-B: 16th FLOOR SLAB CONCRETING COMPLETED ON 12th Sep 2012
BLOCK-C : 15th FLOOR SLAB CONCRETING COMPLETED ON 27th Sep 2012
BLOCK-A: 13th FLOOR SLAB CONCRETING COMPLETED ON 26th Sep 2012
BLOCK-D: 11th FLOOR SLAB CONCRETING COMPLETED ON 29th Sep 2012
BLOCK-B: BLOCK WORK COMPLETED UP TO 13TH FLOOR AND WORK IN PROGRESS AT 14TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-C: BLOCK WORK COMPLETED UP TO 11TH FLOOR AND WORK IN PROGRESS AT 12TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-A: BLOCK WORK COMPLETED UPTO 8TH FLOOR AND WORK IN PROGRESS AT 9TH FLOOR , EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-D: BLOCK WORK COMPLETED UPTO 7TH FLOOR AND IN PROGRES AT 8TH FLOOR.
CLUB HOUSE & SWIMMING POOL AREA: FOUNDATION & COLUMN CONCRETING IN PROGRESS
SWIMMING POOL AREA: SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORKS IN PROGRESS
FIRE FIGHTING PIPE WELDING WORK IN PROGRESS
PLUMBING WASTE/SOIL PIPE LAYING WORKS IN PROGRESS AT CELLAR LEVEL FOR ALL FOUR BLOCKS
PPR PIPING WORKS IN PROGRESS AT TOILET AREAS IN ALL FOUR BLOCKS
WASTE/SOIL PIPE LAYING WORK IN PROGRESS AT ALL FOUR BLOCKS.
INTERNAL ELECTRICAL WORKS IN PROGRESS AT ALL FOUR BLOCKS