Gallery / Monthly Progress Photos. / September 2012

BLOCK-B: 16th FLOOR SLAB CONCRETING COMPLETED ON 12th Sep 2012

BLOCK-C : 15th FLOOR SLAB CONCRETING COMPLETED ON 27th Sep 2012

BLOCK-A: 13th FLOOR SLAB CONCRETING COMPLETED ON 26th Sep 2012

BLOCK-D: 11th FLOOR SLAB CONCRETING COMPLETED ON 29th Sep 2012

BLOCK-B: BLOCK WORK  COMPLETED UP TO 13TH FLOOR AND WORK IN PROGRESS  AT 14TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-C: BLOCK WORK  COMPLETED UP TO 11TH FLOOR AND WORK IN PROGRESS AT 12TH  FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 8TH  FLOOR AND WORK IN PROGRESS AT 9TH FLOOR , EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-D: BLOCK WORK COMPLETED UPTO 7TH FLOOR AND IN PROGRES AT 8TH FLOOR.

CLUB HOUSE & SWIMMING POOL AREA: FOUNDATION & COLUMN CONCRETING IN PROGRESS

SWIMMING POOL AREA: SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORKS IN PROGRESS

FIRE FIGHTING PIPE WELDING WORK IN PROGRESS

PLUMBING WASTE/SOIL PIPE LAYING WORKS IN PROGRESS AT CELLAR LEVEL FOR ALL FOUR BLOCKS

PPR PIPING WORKS IN PROGRESS AT TOILET AREAS IN ALL FOUR BLOCKS

WASTE/SOIL PIPE LAYING WORK IN PROGRESS AT  ALL FOUR BLOCKS.

INTERNAL ELECTRICAL WORKS IN PROGRESS AT ALL FOUR BLOCKS

INTERNAL ELECTRICAL WORKS IN PROGRESS AT ALL FOUR BLOCKS