Gallery / Monthly Progress Photos. / December 2012

BLOCK-B: 19th FLOOR (TERRACE) SLAB CONCRETING COMPLETED

BLOCK-C : 19th FLOOR (TERRACE) SLAB CONCRETING COMPLETED

BLOCK-A: 18th FLOOR SLAB CONCRETING COMPLETED ON 25h Dec 2012

BLOCK-D: 16th FLOOR SLAB CONCRETING COMPLETED ON 31st Dec 2012

BLOCK-B: BLOCK WORK  COMPLETED UP TO 17TH FLOOR AND WORK IN PROGRESS  AT 18TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-C: BLOCK WORK  COMPLETED UP TO 14TH FLOOR AND WORK IN PROGRESS AT 15TH  FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 11TH  FLOOR AND WORK IN PROGRESS AT 12TH & 13TH FLOOR , EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-D: BLOCK WORK COMPLETED UPTO 11TH FLOOR AND IN PROGRES AT 12TH & 13TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS

SWIMMING POOL AREA: SUB-CELLAR SLAB CONCRETING COMPLETED FOR POUR-1

SWIMMING POOL AREA: SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORKS IN PROGRESS FOR POUR-2