BLOCK-B: 19th FLOOR (TERRACE) SLAB CONCRETING COMPLETED
BLOCK-C : 19th FLOOR (TERRACE) SLAB CONCRETING COMPLETED
BLOCK-A: 18th FLOOR SLAB CONCRETING COMPLETED ON 25h Dec 2012
BLOCK-D: 16th FLOOR SLAB CONCRETING COMPLETED ON 31st Dec 2012
BLOCK-B: BLOCK WORK COMPLETED UP TO 17TH FLOOR AND WORK IN PROGRESS AT 18TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-C: BLOCK WORK COMPLETED UP TO 14TH FLOOR AND WORK IN PROGRESS AT 15TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-A: BLOCK WORK COMPLETED UPTO 11TH FLOOR AND WORK IN PROGRESS AT 12TH & 13TH FLOOR , EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-D: BLOCK WORK COMPLETED UPTO 11TH FLOOR AND IN PROGRES AT 12TH & 13TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS
SWIMMING POOL AREA: SUB-CELLAR SLAB CONCRETING COMPLETED FOR POUR-1
SWIMMING POOL AREA: SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORKS IN PROGRESS FOR POUR-2