Gallery / Monthly Progress Photos. / January 2013

BLOCK-B: PARAPET WALL CONCRETING COMPLETED & OHT BASE SLAB WORK IN PROGRESS

BLOCK-C : PARAPET WALL CONCRETING COMPLETED & OHT BASE SLAB WORK IN PROGRESS

BLOCK-A: 19th FLOOR (TERRACE)SLAB CONCRETING COMPLETED ON 23rd Jan 2013

BLOCK-D: 17th FLOOR SLAB CONCRETING COMPLETED ON 22nd Jan 2013

BLOCK-B: BLOCK WORK  COMPLETED UP TO 18TH FLOOR,EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-C: BLOCK WORK  COMPLETED UP TO 16TH FLOOR AND WORK IN PROGRESS AT 17TH  FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 13TH  FLOOR AND WORK IN PROGRESS AT 14TH & 15TH FLOOR , EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-D: BLOCK WORK COMPLETED UPTO 13TH FLOOR AND IN PROGRES AT 14TH & 15TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS

SWIMMING POOL AREA: SUB-CELLAR SLAB CONCRETING COMPLETED FOR POUR-2

CLUB HOUSE AREA: SUB-CELLAR SLAB SHUTTERING & IN PROGRESS ALONG WITH FOUNDATION & COLUMN CONCRETING WORKS