Gallery / Monthly Progress Photos. / May 2013

SWIMMING POOL CELLAR SLAB CONCRETING COMPLETED , SHUTTERING & REINFORCEMENT WORKS IN PROGRESS FOR CELLAR SLAB OF CLUB HOUSE

BLOCK-B: BLOCK WORK  COMPLETED UP TO 19TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 17TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH FLOOR TO GROUND

BLOCK-C: BLOCK WORK  COMPLETED UP TO 18TH FLOOR & WORK IN PROGRESS AT 19TH  FLOOR, INTERNAL PLASTER COMPLETED UP TO 15TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 18TH  FLOOR AND WORK IN PROGRESS AT 19TH FLOORS, INTERNAL PLASTER COMPLETED UP TO 15TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-D: BLOCK WORK COMPLETED UPTO 17TH FLOOR AND IN PROGRES AT 18TH & 19TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 8TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS