Gallery / Monthly Progress Photos. / April 2013

BLOCK-C: STRUCTURAL WORKS FOR ABOVE TERRACE SLAB COMPLETED

BLOCK-A : LMR TOP SLAB &PERGOLA SHUTTERING & REINFORCEMENT IN PROGRESS

BLOCK-D: LMR BOTTOM SLAB &PERGOLA SHUTTERING & REINFORCEMENT IN PROGRESS

CLUB HOUSE & SWIMMING POOL AREA: REINFORCEMNT WORK IN PROGRESS FOR CELLAR SLAB

BLOCK-B: BLOCK WORK  COMPLETED UP TO 19TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 13TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-C: BLOCK WORK  COMPLETED UP TO 18TH FLOOR & WORK IN PROGRESS AT 19TH  FLOOR, INTERNAL PLASTER COMPLETED UP TO 11TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 17TH  FLOOR AND WORK IN PROGRESS AT 18TH & 19TH FLOORS, INTERNAL PLASTER COMPLETED UP TO 14TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-D: BLOCK WORK COMPLETED UPTO 16TH FLOOR AND IN PROGRES AT 17TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 7TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS

PCC WORKS IN PROGRESS AT SUB-CELLAR AREA

PCC WORKS IN PROGRESS AT SUB-CELLAR AREA