BLOCK-C: STRUCTURAL WORKS FOR ABOVE TERRACE SLAB COMPLETED
BLOCK-A : LMR TOP SLAB &PERGOLA SHUTTERING & REINFORCEMENT IN PROGRESS
BLOCK-D: LMR BOTTOM SLAB &PERGOLA SHUTTERING & REINFORCEMENT IN PROGRESS
CLUB HOUSE & SWIMMING POOL AREA: REINFORCEMNT WORK IN PROGRESS FOR CELLAR SLAB
BLOCK-B: BLOCK WORK COMPLETED UP TO 19TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 13TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-C: BLOCK WORK COMPLETED UP TO 18TH FLOOR & WORK IN PROGRESS AT 19TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 11TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-A: BLOCK WORK COMPLETED UPTO 17TH FLOOR AND WORK IN PROGRESS AT 18TH & 19TH FLOORS, INTERNAL PLASTER COMPLETED UP TO 14TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-D: BLOCK WORK COMPLETED UPTO 16TH FLOOR AND IN PROGRES AT 17TH FLOOR, INTERNAL PLASTER COMPLETED UP TO 7TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS