BLOCK-B: 19th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK NEAR COMPLETION
BLOCK-C : 18th FLOOR SLAB CONCRETING COMPLETED ON 18th Nov 2012
BLOCK-A: 16th FLOOR SLAB CONCRETING COMPLETED ON 16th Nov 2012
BLOCK-D: 14th FLOOR SLAB CONCRETING COMPLETED ON 25th Nov 2012
BLOCK-B: BLOCK WORK COMPLETED UP TO 16TH FLOOR AND WORK IN PROGRESS AT 17TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-C: BLOCK WORK COMPLETED UP TO 13TH FLOOR AND WORK IN PROGRESS AT 14TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-A: BLOCK WORK COMPLETED UPTO 11TH FLOOR AND WORK IN PROGRESS AT 12TH & 13TH FLOOR , EXTERNAL PLASTER WORK IN PROGRESS
BLOCK-D: BLOCK WORK COMPLETED UPTO 10TH FLOOR AND IN PROGRES AT 11TH & 12TH FLOOR.
SWIMMING POOL AREA: SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS
CLUB HOUSE AREA: FOUNDATION PCC & RCC WORKS ARE IN PROGRESS