Gallery / Monthly Progress Photos. / November 2012

BLOCK-B: 19th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK NEAR COMPLETION

BLOCK-C : 18th FLOOR SLAB CONCRETING COMPLETED ON 18th Nov 2012

BLOCK-A: 16th FLOOR SLAB CONCRETING COMPLETED ON 16th Nov 2012

BLOCK-D: 14th FLOOR SLAB CONCRETING COMPLETED ON 25th Nov 2012

BLOCK-B: BLOCK WORK  COMPLETED UP TO 16TH FLOOR AND WORK IN PROGRESS  AT 17TH FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-C: BLOCK WORK  COMPLETED UP TO 13TH FLOOR AND WORK IN PROGRESS AT 14TH  FLOOR, EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-A: BLOCK WORK  COMPLETED UPTO 11TH  FLOOR AND WORK IN PROGRESS AT 12TH & 13TH FLOOR , EXTERNAL PLASTER WORK IN PROGRESS

BLOCK-D: BLOCK WORK COMPLETED UPTO 10TH FLOOR AND IN PROGRES AT 11TH & 12TH FLOOR.

SWIMMING POOL AREA: SUB-CELLAR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

CLUB HOUSE AREA: FOUNDATION PCC & RCC WORKS ARE IN PROGRESS