BLOCK-B: (SOUTH-WEST VIEW) BLOCK WORK COMPLETED UP TO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 19TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH FLOOR TO GROUND

BLOCK-B: (SOUTH-EAST VIEW) BLOCK WORK  COMPLETED UP TO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 19TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH FLOOR TO GROUND

BLOCK-C: (NORTH VIEW) BLOCK WORK  COMPLETED UP TO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 18TH FLOOR, WORK IN PROGRESS AT 19TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH TO GROUND FLOOR

BLOCK-C: (EAST VIEW) BLOCK WORK  COMPLETED UP TO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 18TH FLOOR, WORK IN PROGRESS AT 19TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH TO GROUND FLOOR

BLOCK-A: (WEST VIEW) BLOCK WORK  COMPLETED UPTO 19TH  FLOOR. INTERNAL PLASTER COMPLETED UP TO 18TH FLOOR, WORK IN PROGRESS AT 19TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS.

BLOCK-A: (NORTH-EAST VIEW) BLOCK WORK  COMPLETED UPTO 19TH  FLOOR. INTERNAL PLASTER COMPLETED UP TO 18TH FLOOR, WORK IN PROGRESS AT 19TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS.

BLOCK-D: (SOUTH-EAST VIEW) BLOCK WORK COMPLETED UPTO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 11TH FLOOR . EXTERNAL PLASTER WORK IN PROGRESS