Gallery / Monthly Progress Photos. / August 2013

BLOCK-B: (NORTH VIEW) BLOCK WORK & INTERNAL PLASTERING WORKS COMPLETED UP TO 19TH FLOOR. EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH FLOOR TO GROUND

BLOCK-C: (EAST VIEW) BLOCK WORK  & INTERNAL PLASTER COMPLETED UP TO 19TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH TO GROUND FLOOR

BLOCK-A: (SOUTH VIEW) BLOCK WORK & INTERNAL PLASTER WORKS COMPLETED UP TO 19TH FLOOR & WORK IS IN PROGRESS AT EXTERNAL SIDE-19TH TO GROUND FLOOR

BLOCK-D: (NORTH VIEW) BLOCK WORK COMPLETED UPTO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 13TH FLOOR . EXTERNAL PLASTER WORK IN PROGRESS

CLUB HOUSE: GROUND FLOOR SLAB CONCRETING COMPLETED ON 7TH AUG 2013 & WORK IN PROGRESS FOR 1ST FLOOR SLAB