BLOCK-B: (SOUTH VIEW)-EXTERNAL PLASTER WORKS ARE NEAR COMPLETION- 19TH TO GROUND FLOOR
BLOCK-B: (EAST VIEW)-EXTERNAL PLASTER WORKS ARE NEAR COMPLETION- 19TH TO GROUND FLOOR
BLOCK-C: (NORTH EAST VIEW) EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH TO GROUND FLOOR
BLOCK-C: (WEST VIEW) EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH TO GROUND FLOOR
BLOCK-A: (EAST VIEW) EXTERNAL WORK IS IN PROGRESS-19TH TO GROUND FLOOR
BLOCK-D: (SOUTH EAST VIEW) BLOCK WORK COMPLETED UPTO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 17TH FLOOR . EXTERNAL PLASTER WORK IN PROGRESS
CLUB HOUSE: 2ND FLOOR SLAB CONCRETING COMPLETED ON 8TH OCT 2013