BLOCK-B: (NORTH VIEW)-EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH FLOOR TO GROUND
BLOCK-B: BLOCK WORK & PLASTERING COMPLETED FOR PERGOLAS & LMR’S
BLOCK-A: BLOCK WORK COMPLETED & PLASTERING COMPLETED FOR PERGOLAS & IS IN PROGRESS FOR LMR’S
BLOCK-C: (SOUTH EAST VIEW) BLOCK WORKÂ & INTERNAL PLASTER COMPLETED UP TO 19TH FLOOR & EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH TO GROUND FLOOR
BLOCK-A: (NORTH VIEW) BLOCK WORK & INTERNAL PLASTER WORKS COMPLETED UP TO 19TH FLOOR & WORK IS IN PROGRESS AT EXTERNAL SIDE-19TH TO GROUND FLOOR
BLOCK-D: (NORTH WEST VIEW) BLOCK WORK COMPLETED UPTO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 15TH FLOOR . EXTERNAL PLASTER WORK IN PROGRESS