Gallery / Monthly Progress Photos. / December 2013

BLOCK-B: (SOUTH VIEW)-EXTERNAL PLASTER WORKS ARE NEAR COMPLETION- 19TH TO GROUND FLOOR

BLOCK-B:(EAST VIEW)-EXTERNAL PLASTER WORKS ARE NEAR COMPLETION- 19TH TO GROUND FLOOR

BLOCK-C: (SOUTH EAST VIEW) EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH TO GROUND FLOOR

BLOCK-C: (SOUTH WEST VIEW) EXTERNAL PLASTER WORK IN PROGRESS FROM 19TH TO GROUND FLOOR

BLOCK-A: (NORTH VIEW) EXTERNAL WORK IS IN PROGRESS-19TH TO GROUND FLOOR

BLOCK-D: ( NORTH VIEW) BLOCK WORK COMPLETED UPTO 19TH FLOOR. INTERNAL PLASTER COMPLETED UP TO 19TH FLOOR . EXTERNAL PLASTER WORK IN PROGRESS

CLUB HOUSE: PARAPET WALL CONCRETING COMPLETED